“The 48-Hour Pre-Offer Checklist” — class status, PSC hits, corrosion flags, yard slots, parts lead times

“The 48-Hour Pre-Offer Checklist” — class status, PSC hits, corrosion flags, yard slots, parts lead times

Buying a ship under time pressure is about reducing unknowns fast. In 48 hours you can surface the big risks, class and statutory status, PSC patterns, corrosion/steel exposure, docking windows, and parts lead times, so you only spend survey money on vessels that deserve it. Use this field-tested flow to request once, triage quickly, and protect your offer.

48-Hour Pre-Offer Checklist

Class & statutory reality, PSC patterns, corrosion signals, docking windows, parts risk — fast triage so you only chase ships worth surveying.

Class status PSC history Steel & coatings Yard slots Lead times
Time budget≤ 48 hrs
Pass early1 Red = Stop
Proceed w/ terms2 Ambers
Proceed cleanAll Green

Timeline: What to Do, When

Hours 0–6 — “Request Once” Pack. Ask for one link/zip: class status & due list; all statutory certs; last 24 months surveys/drydock + UT & coating matrices; last 2–3 PSC reports; ME/AE hours + overhauls + critical spares; BWTS/scrubber/NOx docs; drydock history & next due; last 90-day AIS port list; Q88/particulars; lien/encumbrance letter.
Hours 6–12 — Class & Statutory reality. Extract due dates; list Conditions of Class (CoC)/memos; mark any overdue items. Tally PSC deficiency codes and repeats.
Hours 12–24 — Corrosion / Steel scan. Compare UT to original scantlings; focus ballast tanks, wind/water line, deck penetrations, hopper corners; map renewals from last dock.
Hours 24–36 — Yard & parts. Confirm docking drivers; “anonymous” slot checks with 2–3 yards on route; ask OEMs about flagged spares lead times.
Hours 36–48 — Commercial sanity + protections. Verify speed/consumption vs. recent logs; check CII/EEXI docs; validate trading pattern vs. intended use; draft LOI conditions (subject to survey/sea trial/records).

Class Status

Current status report, CoC/recommendations, memoranda, survey-due calendar.

Predicts mandatory spend & off-hire.

Statutory Certificates

Load Line • SOLAS (S-Constr/Equip/Radio) • IAPP/IOPP/IEEC • ISM DOC/SMC • ISPS • MLC • EIAPP/NOx • BWTS approvals + exemptions.

Confirm expiries around handover.

Surveys & Dock

Annual/Intermediate/Special; last drydock report; UT tables; ballast/cargo coating matrices.

Reveals steel & coating scope next dock.

PSC History

Last 2–3 PSC reports with codes and closure evidence; note detentions and repeats.

Operational culture & detainability.

Machinery & Spares

ME/AE hours; latest overhauls; lube analyses; critical spares list; automation/controls alarm logs.

Overhaul timing & supply risk.

Commercial & Legal

Speed/consumption curves; cargo gear certs; 12-month trading pattern; H&M/P&I claim abstracts; lien/encumbrance statement.

Performance reality & title cleanliness.

Green / Amber / Red — Fast Triage

Two Ambers in the same system → renegotiate price/terms or pass. One serious Red → stop.

Class & CoC

Green: No CoC; routine due dates > 6–12 months.
Amber: Minor CoC with seller’s rectification plan pre-delivery.
Red: Multiple/major CoC; overdue; memorandum restricting trade.

PSC Pattern

Green: Low severity; no repeats.
Amber: Repeat admin/ISM items.
Red: Recent detention; repeat critical codes (fire, lifesaving, propulsion).

Steel & Coatings

Green: UT within ~10% of original; ballast “Good/Fair”.
Amber: Localized 10–20% thinning; small renewals last dock.
Red: Wide >20% loss; “Poor” in multiple tanks; major renewals pending.

Corrosion & Steel: 30-Minute Quick Screen

Ballast tanks — UT vs. original, coating rating, renewals map

“Poor” coatings or >20% thinning in knuckles/corners → expect steel next dock; plan targeted UT during survey.

Deck plating — pitting clusters, scuppers, penetrations, crane pedestals

Rust jacking and pitting near penetrations often escalate hot-work hours.

Wind / Water line — strake readings at WL ±0.5 m; fairing plates

High loss indicates coating age and likely fairing repairs.

Hoppers & longitudinals — web/flange UT, bracket toes

Loss at bracket toes is a common surprise; budget time and permits in dock.

Targeted UT Points (print this)

  • 2–3 spots per ballast tank knuckle/corner
  • WL strakes fwd/mid/aft (port & starboard)
  • Deck penetrations & crane pedestal rings
  • Hopper brackets at frame transitions

No recent UT provided = treat as Amber until verified.

Yard Window & Parts Risk

Docking Checklist

  • Confirm class/statutory drivers requiring drydock (tail-shaft, steering, prop tests).
  • List items to close in dock from CoC/memos and surveys.
  • Ping 2–3 yards on route for anonymous slot checks (duration, crane limits).
  • Ask for prior dock scope & contractor notes (blast areas, steel tonnage).

Typical Lead Times

CategoryLead Time*Do Now
Class consumables1–3 weeksMatch on-hand spares to survey kit; pre-reserve if dock near.
ME/AE critical spares2–8+ weeksOEM stock status by part #; check exchange programs.
Seals/shafts/props3–10+ weeksConfirm dimensions; request conditional quotes (Incoterms).
Nav/automation1–6 weeksVerify licenses/keys & support status.
BWTS/scrubber2–12 weeksConfirm maker/model approvals; sensor/UV availability.

*Indicative; verify with OEM/authorized distributor.

Offer Conditions to Protect You

Examples to Copy

  • Hidden class items: “Sale subject to no new CoC/memoranda pre-delivery; seller to rectify existing CoC at own cost.”
  • Steel uncertainty: “Buyer may perform targeted UT & coating survey; if renewals exceed [X tons] or [Y hours], price adjust or withdraw.”
  • PSC risk: “Seller to rectify repeat PSC deficiencies prior to delivery and provide evidence.”
  • Parts delays: “Back-to-back delivery with assigned POs for critical spares or price escrow until receipt.”
  • Encumbrances: “Clean title letter + deletion certificate as conditions precedent to payment.”

Email Script — Pre-Offer Pack

Subject: [Vessel] – 48-Hour Pre-Offer Pack

Hi [Broker/Owner],
Please share one link/zip with:
• Class status, CoC/memos, survey due list
• Statutory certs + expiries
• Last 24 months surveys/drydock, UT & coating matrices
• Last 2–3 PSC reports
• ME/AE hours, overhauls, critical spares
• BWTS/scrubber/NOx docs
• Drydock history & next due; 90-day AIS list
• Q88/particulars; lien/encumbrance statement
Thanks—this lets us move to a conditional LOI quickly.

Go / No-Go — Make the Call

Proceed

All Green; only minor Ambers with clear fixes.

Next: conditional LOI → book survey & targeted UT.

Proceed with Terms

One Red (manageable) or clustered Ambers in one system.

Next: seller rectification/escrow; adjust delivery window/price.

No-Go

Multiple Reds across class/steel/PSC or unverified criticals.

Next: pass; redeploy time to stronger candidates.

This framework is a pre-offer triage, not a substitute for full condition survey and sea trial. If it passes here, it’s worth deeper money.